How Much Does It Cost to Build a House in the Philippines per Square Meter (2026)?

Two-storey concrete house under construction on a provincial subdivision lot in the Philippines at golden hour with the owners thinking about the construction cost.

Imagine an OFW nurse in Riyadh with a 150 sqm lot in Lipa, Batangas, and ₱2 million saved to build an 80 sqm family home. Then the quotes arrive: one contractor asks for ₱1.6 million, another ₱2.4 million, and a third ₱3.1 million.

None of them is necessarily overcharging. Dividing each quote by 80 gives ₱20,000, ₱30,000 and about ₱38,750 per square meter—representing an economy, standard and near-premium build. They are pricing three different types of houses. None of the quotes includes the plans, permits, fence or contingency costs she will also need to pay.

The problem with asking how much it costs to build a house in the Philippines per square meter is that there is no single answer. Costs vary by finish level, house type, and location. This 2026 guide covers current rates, hidden costs, three sample budgets, a calculator, and the documents your lot needs before construction begins.

Building a House in 2026: The Quick Answer
  • Construction runs ₱20,000 to ₱55,000+ per sqm. Economy ₱20K–26K, standard ₱27K–38K, mid-high ₱38K–55K, high-end ₱55K and up.
  • A 100 sqm standard house costs about ₱2.7M–₱3.8M to build, before land, plans and permits.
  • Add at least 20–30% for what the per-sqm quote leaves out: professional fees, permits, soil test, site work, fence, utility connections and contingency.
  • Prices are rising. Metro Manila wholesale material prices were up 3.4% year on year in September 2026, and another cement increase is being considered.
  • Fix the papers first. No building permit or construction loan moves without a clean title and tax declaration in your name.

In 2026, building a typical concrete house costs about ₱20,000 to ₱55,000 or more per square meter. Most family homes cost between ₱27,000 and ₱38,000 per square meter. These are AEDO Construction’s planning estimates, updated October 1.

Finish levelPer sqm60 sqm100 sqm150 sqm
Economy₱20,000–26,000₱1.20M–1.56M₱2.00M–2.60M₱3.00M–3.90M
Standard₱27,000–38,000₱1.62M–2.28M₱2.70M–3.80M₱4.05M–5.70M
Mid-high₱38,000–55,000₱2.28M–3.30M₱3.80M–5.50M₱5.70M–8.25M
High-end₱55,000+₱3.30M+₱5.50M+₱8.25M+
Construction only, gross floor area (all floors). Excludes land, professional fees, permits, site work, fence and furniture. Source: AEDO Construction 2026 planning ranges, updated Oct. 1, 2026.

Finish level affects the total cost more than size: a 100 sqm mid-high house can cost more than a 150 sqm economy one. These figures cover construction only. Land, plans, permits, and other hidden costs come extra.

The PSA figure vs. a contractor’s quote

The Philippine Statistics Authority reported much lower figures. New buildings approved in August 2026 cost an average of ₱14,357 per square meter, up 21.9% from the previous year. Residential buildings averaged about ₱14,082 per square meter in May 2026.

You can’t build a house for ₱14,000 per square meter. The PSA figure is the average value listed on building permits nationwide, including basic provincial and socialized homes. It is declared before construction starts and often kept low because some permit fees are based on it. Use it as a trend: if it rises 20% in a year, contractor prices are likely rising too.

Two kinds of “cost per sqm”
Gold: PSA averages from building permit applications. Terracotta: midpoints of 2026 contractor planning ranges.
PSA residential average (May 2026)₱14,082
PSA all new constructions (Aug. 2026)₱14,357
Contractor economy midpoint₱23,000
Contractor standard midpoint₱32,500
Contractor mid-high midpoint₱46,500

PSA figures are estimated values declared on permit applications, averaged nationwide. They show the trend, not what a contractor will quote you. Sources: PSA; AEDO Construction.

Construction cost vs. all-in project cost

A per-sqm quote covers the house itself, including the structure, roof, walls, windows and doors, wiring, plumbing, and finishes. It usually does not include professional fees, permits, soil tests, site work, fencing, utility connections, or furniture. AEDO estimates these extras typically add 20–30%, or more when a full fence is included.

Floor area, not lot area

Contractors charge by total floor area, adding all floors together. A two-storey house with a 60 sqm footprint has 120 sqm of floor area. Lot size affects the budget only through site work and fencing.

Bungalow or two storeys? The cost per square meter is often similar. A bungalow needs more foundation and roof, while a two-storey house needs a suspended slab, stairs and stronger columns. Ask your engineer to price both options. On a narrow city lot, the lot may decide for you.

Finish level is the biggest factor in your budget. Here’s what each level generally includes, based on AEDO’s 2026 descriptions.

EconomyStandardMid-highHigh-end
FloorsPlain cement finishCeramic tilesGranite or homogeneous tilesPremium stone, wood or imported tiles
WallsPlastered CHB, basic paintPlastered and paintedBetter paint systems, feature wallsArchitectural finishes, custom details
WindowsBasic jalousie or steelAluminumUPVCSpecified systems, large glazing
FixturesBasic localMid-rangeBetter brandsImported, custom millwork
Typical ownerStarter or rental houseMost family homesUpgraded family homeCustom-designed home

Where to spend and where to save

Spend on things that are costly to fix later, like the structure, roof, and waterproofing. Save on items you can upgrade later, such as fixtures, lights, cabinets, and some tiles.

Spend here (hard to fix later)
  • Foundation, columns and beams
  • Roof framing, roofing and gutters
  • Waterproofing of slabs, bathrooms and roof decks
  • Electrical wiring and plumbing inside the walls
Save here (easy to upgrade)
  • Faucets, light fittings and switches
  • Kitchen cabinets and countertops
  • Bedroom floor tiles
  • Decorative ceilings and feature walls

House type also affects the price because of its structure and plumbing. Shared walls make row houses and duplexes cheaper per unit, while rental buildings with a kitchen and bathroom in each unit can cost almost as much as full houses.

House typeCost per sqmBest forWatch out for
BungalowYour finish bandWide lots, aging parents, provincesLarger foundation and roof per sqm
Two-storeyYour finish bandSubdivision lots of 100–200 sqmSuspended slab, stairs, heavier columns
Three-storeyUpper half of your bandNarrow city lotsHeavier structure; engineer review is a must
Duplex / row houseYour band; shared walls cut cost per unitRentals, family compoundsFirewall and setback rules
Boarding house₱18,000–24,000Bedspace rentals near schools and officesShared CRs, fire safety, business permits
Apartment (own kitchen and CR)₱25,000–35,000Long-term rentalsPlumbing and fixtures multiply per unit
Prefab / modular₱10,000–20,000 (structure)Fast, budget buildsFoundation, utilities and add-ons are extra
Rental-building and prefab ranges: AEDO Construction (2026) and our Prefab Homes guide. Construction only.

If a standard home is too expensive, prefab can lower construction costs, but foundations, utilities, and finishing work often cost more than buyers expect.

Related Guide
Prefab Homes in the Philippines (2026): Real Costs, Typhoon Safety, Financing, and How to Choose a Builder
When a factory-built house really saves money, and the add-ons that close the gap.

Metro Manila and Metro Cebu have the highest construction costs in the country. AEDO says labor in the provinces is 15–25% cheaper, but transport to remote areas can reduce the savings. Cement can also cost 15–25% more on island provinces and in places far from a plant.

Labor is also becoming more expensive. In late September 2026, the NCR daily minimum wage increased from ₱695 to ₱755 under Wage Order No. NCR-28. Skilled masons and carpenters charge even more.

Hazard-resistant design increases building costs. Areas in typhoon zones need stronger roofs, while properties near active faults need foundations that follow the National Structural Code (NSCP 2015). Check both before buying with our flood and fault-line risk guide.

Baseline
Metro Manila, Metro Cebu
Highest labor rates; use the full band
−5%
Growth provinces
Cavite, Laguna, Batangas, Rizal, Bulacan, Pampanga
−8%
Other provinces
Mainland towns with nearby suppliers
+5%
Islands, remote sites
Hauling and freight cancel out cheaper labor

Indicative adjustments used in our calculator below. They are U-Property PH planning assumptions based on AEDO’s estimate that provincial labor runs 15–25% cheaper, not published rates. Get local quotes.

Cost by construction stage

AEDO’s sample budget for a 100 sqm house shows how the costs are divided. Structural work takes the largest share at about 28%, followed by tiles and finishes, masonry and waterproofing, and doors and windows.

Where ₱2.7M–₱3.9M goes: 100 sqm standard house
Structural works
28%
Tiles and finishes
13%
Masonry, waterproofing
12%
Overhead, contingency
11%
Doors and windows
10%
Roofing
9%
Electrical
7%
Plumbing
6%
Painting
4%

Shares of AEDO Construction’s sample 2026 budget for a 100 sqm standard house (₱2.72M–₱3.94M, construction only).

2026 material prices

Use these to check prices on any bill of materials you receive.

Material2026 price range
Portland cement, 40 kg bag₱260–300
Deformed steel bar, 12 mm × 6 m₱220–250
Concrete hollow block, 4″₱18–24 each
Plywood, ½″ 4×8₱580–680
Ceramic floor tile₱350–600 per sqm
Metro Manila hardware prices per AEDO Construction (updated Oct. 1, 2026). Island provinces can run 15–25% higher for cement. Always get a current local quote.

Cement prices may not stay at that level. Concreat Holdings, which raised prices by about ₱30 per bag in March, said in early November that it may raise them again by ₱28 to ₱40 per bag.

Pakyaw, daily rate or full contractor?

With pakyaw, you pay a crew a fixed amount for labor and provide the materials. With a daily rate, you pay workers each day and take the risk if the work is slow. A full contractor provides both labor and materials for one total price, including overhead and profit.

Pakyaw may look cheaper, but you must manage the project, order materials, check quantities, and cover waste. It works if you or a trusted relative can visit the site often. If you live abroad, a licensed contractor with a fixed-price contract is usually worth the extra cost.

This is where most self-build budgets go wrong. Include these costs before deciding what you can afford.

Add these to your construction budget
Architect and engineer feesDesign, signed and sealed plans, specs and bill of materials
8–12% of construction
Building permit and clearancesAncillary permits, fire safety evaluation, barangay and zoning
₱30,000–100,000+
Soil boring testPer borehole, about 10 m deep, before mobilization
₱25,000–35,000
Survey, site clearing and fillMore on sloping, low-lying or occupied lots
Varies by lot
Fence, gate and drainageOften required by subdivision rules
Get a separate quote
Power, water and septic connectionsMeralco or your electric co-op, water utility, septic tank
Ask your utilities
Occupancy permitRequired before you move in
Small; LGU fee schedule
ContingencyFor price changes and surprises on site
10–15% of construction
Typical total: 20–30% on top of construction, more with a full perimeter fence

The fence is often the biggest surprise for owners. It can cost hundreds of thousands of pesos, and many subdivisions have rules on its design and height under their Deed of Restrictions.

Enter your floor area, finish level, and location to get a 2026 cost estimate. The calculator includes professional fees, permits, and contingency, but excludes land, fencing, and furniture.

2026 House Construction Cost Calculator
Construction–
Professional fees (8–12%)–
Permits and clearances–
Contingency–
Estimated total–

Planning estimate only. Excludes land, soil test, site work, fence, utility connections and furniture. Rates: AEDO Construction 2026 bands (high-end capped at ₱75K for this tool); location factors and permit range are U-Property PH assumptions.

Use the result to verify quotes, not replace them. Sign a contract only when the bill of quantities comes from a licensed engineer or architect.

These budgets use average rates and include the hidden costs listed above. The numbers are examples, but each line shows a real cost.

Budget A
60 sqm economy bungalow, provincial lot (Batangas)
Construction (60 sqm × ₱23,000)₱1.38M
Professional fees (8%)₱110K
Permits and clearances₱35K
Survey, site prep₱60K
Fence and gate₱120K
Utility lines, septic₱60K
Contingency (10%)₱138K
All-in estimate₱1.90M
38% above construction alone · about ₱31,700 per sqm all-in
Budget B
100 sqm standard two-storey, subdivision lot (Cavite)
Construction (100 sqm × ₱32,000)₱3.20M
Professional fees (10%)₱320K
Permits and clearances₱60K
Soil boring test₱30K
Survey, site prep₱80K
Fence and gate₱150K
Utility lines, septic₱80K
Contingency (10%)₱320K
All-in estimate₱4.24M
32% above construction alone · about ₱42,400 per sqm all-in
Budget C
150 sqm mid-high house, Quezon City
Construction (150 sqm × ₱46,000)₱6.90M
Professional fees (10%)₱690K
Permits and clearances₱100K
Soil boring test₱60K
Survey, site prep₱150K
Fence and gate₱200K
Utility lines, septic₱100K
Contingency (12%)₱828K
All-in estimate₱9.03M
31% above construction alone · about ₱60,200 per sqm all-in

Illustrative budgets by U-Property PH. Construction rates are mid-band AEDO 2026 figures; fees, permits and soil tests use the ranges above; site work, fence and utility lines are planning allowances. Land not included.

All three cost 31–38% more than construction alone, exceeding AEDO’s 20–30% estimate because they include full fencing and utility lines. Treat 20–30% as the minimum, not the maximum. Smaller homes have higher fixed costs, which is why Budget A has the largest markup.

Material prices were mostly unchanged early in 2026. The Middle East conflict later raised fuel and shipping costs. PSA data shows that construction material prices in Metro Manila rose 0.9% year on year in January and 3.6% in August, the fastest increase in three years, before slowing to 3.4% in September. Concrete, sand, and gravel had the biggest price increases.

Construction material prices picked up through 2026
NCR Construction Materials Wholesale Price Index, year-on-year growth (%)
0.9
1.0
1.1
1.9
2.8
2.9
3.5
3.6
3.4
JanFebMarAprMayJunJulAugSep

August’s 3.6% was the fastest in three years. Source: Philippine Statistics Authority, as reported by BusinessWorld, BusinessMirror, Daily Tribune and The Freeman.

Big contractors prepared for higher costs. In a Philippine Constructors Association survey reported by Philstar in March, members expected material prices to rise by up to 30%. The peso later fell to about ₱63 per dollar in the third quarter, making imported fixtures and steel more expensive. Owners delayed projects. In August 2026, approved building permits fell 31% from a year earlier, reaching their lowest level since May 2020.

Should you build now or wait?

Waiting probably won’t make your house cheaper: wages have risen, and cement prices may increase again. You can control your exposure:

  • Lock prices on the big items. Ask for a fixed-price contract, or buy cement and rebar in batches as each stage starts. Don’t stockpile cement; it hardens in storage.
  • Phase by design, not by accident. If you must build in two stages, have the engineer design the foundation and columns for the finished house from day one.
  • Work around the rains. Plan the foundation and roof for the dry months, roughly December to May in much of Luzon.

No bank, Pag-IBIG office, or building official will process your project until the lot’s papers are complete. Take care of three things first.

1. The right type of lot

Subdivision lots, rural lots, and agricultural land have different rules. Subdivision lots often have restrictions on home size, setbacks, height, and fences, and some require HOA approval. Agricultural land may need to be converted before you can legally build a house.

Related Guide
Buying Land in the Philippines: Residential Lot Types Explained for Metro Manila and Nearby Provinces
Subdivision, open and agricultural lots compared: rules, risks and what each lets you build.

2. A clean title in the right name

The building permit application asks for the lot’s TCT and tax declaration numbers. Before lending for construction, Pag-IBIG requires the title, tax declaration, and latest real property tax receipt. Building a ₱3 million house on land with only a tax declaration is risky because lenders prefer titled property, and a tax declaration does not prove ownership. Read Tax Declaration vs. Title before building on untitled land.

3. A higher amilyar afterwards

Once the house is finished, the assessor adds its value to the property, increasing your yearly real property tax. Our amilyar guide explains how it is calculated.

Paper check before you pay for plans
  1. Title in your name (or with a signed deed and transfer under way), verified with the Registry of Deeds.
  2. Tax declaration for the land, matching the title’s lot number and area.
  3. Latest real property tax receipt, with no arrears.
  4. Deed of Restrictions or HOA design rules, if the lot is in a subdivision.
  5. Zoning and hazard check: confirm the lot is residential and check its flood and fault-line exposure.

Pag-IBIG’s housing loan can fund construction on your own lot, with loans of up to ₱10 million and repayment terms of up to 30 years. Applications submitted by December 31, 2026 qualify for a three-year fixed promo rate: 4.5% for loans up to ₱4.9 million and 5.75% for larger loans.

The trade-off is more paperwork and a slower process. Pag-IBIG requires plans, specifications, and a materials list signed by a licensed engineer or architect, along with proof of ownership. It releases the loan in stages after checking the work, so you or your contractor must pay for each stage before receiving the next payment.

Banks are usually faster but cost more, as the table shows.

Pag-IBIG housing loanBank construction loan
Maximum loan₱10 millionBased on appraisal and income
Rate (2026)4.5% up to ₱4.9M; 5.75% above, fixed 3 years (applications until Dec. 31, 2026)Metrobank 6.25%–8.25%; BPI 7.00%–12.00%, by fixing period
TermUp to 30 yearsUp to 20–25 years
Loan-to-valueSubject to appraisalUp to 80% (Metrobank, BDO); up to 90% (BPI)
Who qualifiesMembers with 24 monthly contributionsTypically ₱40,000+ monthly household income
ReleaseIn tranches after site inspectionsIn tranches by progress
Terms as published mid-2026 and compiled by AEDO Construction (re-checked Sept. 2026). Confirm current rates with Pag-IBIG and your bank before applying.

For eligibility, read our Pag-IBIG housing loan guide. To estimate your affordable monthly payment, use our salary-to-afford-a-home guide.

Building is best when you own the lot and can oversee the work. Buying is best when time, distance, or financing is limited.

Build if…
  • You already own the lot, or got it cheaply
  • You want a layout no developer sells
  • You or someone you trust can visit the site often
  • You can wait a year or more to move in
Buy if…
  • You need to move in within months
  • You’re abroad with no reliable representative
  • You’d need to finance the lot and the house
  • You want a fixed price and a finished product to inspect

Use the total cost, not the price per square meter. In Budget B, the ₱3.2 million construction cost rises to about ₱4.24 million after adding fees, permits, site work, the fence, and contingency. Compare this total plus your lot’s market value with nearby finished homes of a similar size.

Most overruns start with the quote. These five habits can help:

  • Ask for a bill of quantities (BOQ), not a per-sqm price. A BOQ lists every material and quantity, so you can compare contractors line by line and see what’s missing.
  • Check licenses. Look the contractor up on PCAB’s verification portal (pcab.construction.gov.ph/verify) and the engineer or architect on PRC’s online verification. Every sheet of your plans should carry their signature and seal.
  • Pay by milestone. Pay against completed stages such as foundation, roof and finishing, never a large lump sum upfront.
  • Put specifications in writing. Brand, size and grade for tiles, roofing, windows and fixtures, so “standard” means the same thing to both of you.
  • Price every change before it starts. Each design change should be quoted and signed off before the crew begins it.

Know your protection. Under Article 1723 of the Civil Code, the engineer, architect, or contractor may be liable if a building collapses within 15 years because of design, construction, or material defects. Small crews must also be licensed, and PCAB now offers a small-scale “pakyaw contractor” license.

Walk away if the contractor…
  • Quotes a single per-sqm price and won’t give a bill of quantities
  • Asks for more than a small mobilization payment before work starts
  • Can’t show a PCAB license, or plans without a PRC seal
  • Leaves brands and grades of materials “to be decided”
  • Suggests starting before the building permit is out
  • Has no completed houses you can visit or owners you can call

Can I build a house for ₱1 million in the Philippines?

Yes, but a small one. At economy rates of ₱20,000–₱26,000 per sqm, ₱1 million covers about 38–50 sqm of construction, and less once plans, permits and contingency are paid. A prefab structure can stretch the budget further.

How much does a 2-bedroom bungalow cost to build in 2026?

A 2-bedroom bungalow is usually 50–70 sqm. At standard rates of ₱27,000–₱38,000 per sqm, construction runs about ₱1.35–₱2.66 million, plus at least 20–30% for fees, permits and extras.

Is it cheaper to build or buy a house?

If you already own the lot, building can cost less than a comparable finished house, but only once you count the all-in cost and your own time. If you would have to buy the lot too, compare the combined cost with finished houses nearby.

Do I need an architect or engineer for a small house?

Yes. The National Building Code requires signed and sealed plans from licensed professionals for a building permit, and Pag-IBIG and banks require them for construction loans. Fees typically run 8–12% of construction cost.

How much should I budget for building permits?

Plan on about ₱30,000 to ₱100,000 or more for the building permit and related clearances, depending on your LGU and floor area. The base building fee is small; ancillary permits, fire safety charges and local fees add to it.

What to Read Next
Buying Land in the Philippines: Residential Lot Types Explained for Metro Manila and Nearby Provinces
Choose the lot before the house: what each lot type allows you to build.
→
Tax Declaration vs. Title: Can You Safely Buy Land With Only a Tax Declaration?
Why a tax declaration alone won’t get you a construction loan, and how to fix it.
→
Prefab Homes in the Philippines (2026): Real Costs, Typhoon Safety, Financing, and How to Choose a Builder
The budget alternative to a conventional build, with real 2026 numbers.
→
Real Property Tax (Amilyar) in the Philippines: How It’s Computed, When to Pay, and How to Avoid Penalties
What your yearly tax looks like once the new house is assessed.
→
Pag-IBIG Housing Loan 2026: Rates, Loan Limits, and How to Qualify for Your First Home
Eligibility, loan limits and the promo rates that apply to construction loans.
→
Planning to Build?

Your House Is Only as Good as the Lot Under It

Browse residential lots in Metro Manila and nearby provinces, or tell U-Property PH where you plan to build. We’ll help you check the lot’s title, restrictions and flood exposure before you spend a peso on plans.

Disclaimer

This article is for general informational purposes only and does not constitute legal, financial, or professional advice. Construction costs, laws, regulations, and fees change. Always consult a licensed real estate broker, engineer, architect, or lawyer for advice specific to your situation.

Sources & References
  1. AEDO Construction: ‘House Construction Cost Philippines 2026’ (published May 17, 2026; updated Oct. 1, 2026): finish-level bands, 100 sqm sample budget, material prices, permit and professional fee ranges, regional labor gap. [aedoconstruction.com]
  2. AEDO Construction: ‘Construction Budget to House Size’: soft costs routinely add 20–30% to construction cost. [aedoconstruction.com]
  3. AEDO Construction: ‘Apartment and Boarding House Construction Cost in the Philippines (2026)’. [aedoconstruction.com]
  4. AEDO Construction: ‘House Construction Loan Philippines 2026: Pag-IBIG vs Bank Financing’ (re-checked Sept. 23, 2026). [aedoconstruction.com]
  5. AEDO Construction: ‘Cement Price Per Bag in the Philippines (2026)’: island and remote areas 15–25% higher. [aedoconstruction.com]
  6. AEDO Construction: ‘Soil Boring Test Cost in the Philippines’: ₱25,000–₱35,000 per borehole. [aedoconstruction.com]
  7. AEDO Construction: ‘How to Verify an Engineer’s PRC and Contractor’s PCAB License’. [aedoconstruction.com]
  8. Philippine Statistics Authority: Construction Statistics from Approved Building Permits, August 2026: average cost of new constructions ₱14,357.01 per sqm, up 21.9%. [psa.gov.ph]
  9. Philippine Statistics Authority: Construction Statistics from Approved Building Permits, May 2026: residential average ₱14,081.64 per sqm. [psa.gov.ph]
  10. Philippine Statistics Authority: Construction Materials Wholesale Price Index in the NCR, September 2026 (3.4% year on year). [psa.gov.ph]
  11. BusinessWorld: ‘NCR construction materials wholesale price growth hits 3-year high in August’ (Sept. 8, 2026). [bworldonline.com]
  12. BusinessWorld: ‘Cement price hikes add to construction cost pressures’ (Nov. 3, 2026): Concreat Holdings’ planned ₱28–₱40 per bag increase; peso at ₱63.23. [bworldonline.com]
  13. BusinessWorld: ‘NCR building material inflation quickens in May’ (June 10, 2026). [bworldonline.com]
  14. The Freeman / Philstar: ‘Prices of construction materials rise at faster pace in January’ (Feb. 16, 2026): NCR CMWPI 0.9% in January. [magzter.com]
  15. Daily Tribune: ‘Construction material costs accelerate in July’ (Aug. 12, 2026). [tribune.net.ph]
  16. BusinessMirror: ‘Drop in approved building permits worries experts’ (Oct. 22, 2026): August permits down 31%, lowest since May 2020. [businessmirror.com.ph]
  17. Philstar: ‘After flood control, contractors brace for war impact’ (Mar. 24, 2026): PCA survey, members expect up to 30% material price hikes. [philstar.com]
  18. SunStar: ‘P60 minimum wage hike takes effect in Metro Manila’: Wage Order No. NCR-28 raises the non-agriculture minimum to ₱755. [sunstar.com.ph]
  19. Republic Act No. 386: Civil Code of the Philippines, Art. 1723 (15-year liability of engineer, architect and contractor for building collapse). [lawphil.net]
  20. PCAB Board Resolution No. 123: Licensing of small-scale contractors (“Pakyaw Contractors License”). [construction.gov.ph]