Metro Manila’s condo glut is real, but it isn’t the market ₱35-million buyers are shopping in. At the top of Makati, one developer paused a tower and kept half its buyers, and another broke ground two months later.

On April 20, 2026, Ayala Land took an unusual step for luxury developers in the Philippines by halting sales of the Laurean Residences, a 67-storey building in Makati’s Legazpi Village that was set to be the tallest residential structure in the country and had already generated over ₱10 billion in sales with fully sold four-bedroom units. Ayala paused the project due to concerns over construction costs and risks related to the US–Iran conflict.
Five months later, Ayala’s CEO reported that half of Laurean’s buyers opted not to take a refund with interest and decided to wait. Meanwhile, on Arnaiz Avenue, Arthaland and its Japanese partner Mitsui Fudosan had already started construction on Sondris, a 37-storey tower expected to generate ₱12 billion in revenue.
The paragraph highlights that the common narrative about Metro Manila’s 24.7% condo vacancy rate and developer pullback doesn’t capture the full picture. While the vacancy rate is true, it represents a different market. This guide will clarify the situation in Makati, the contrasting decisions of two developers nearby, and implications for buyers, holders, or investors at ₱20 million and higher.
- Ayala Land paused Laurean Residences over construction costs and delivery risk, not weak demand. It had sold more than ₱10 billion, including every four-bedroom unit.
- About half of Laurean’s buyers chose to wait for a 2027 decision, even with a full refund with interest on offer.
- Arthaland raised Sondris’s one-bedroom price from ₱21 million to ₱22 million and broke ground in June, after locking in construction costs.
- Metro Manila’s 24.7% vacancy comes mostly from mid-market investor units. High-end projects were only about 5% of unsold inventory in Colliers’ early-2025 count.
- At this tier, what matters is the developer’s staying power, the contract’s pause and refund terms, and whether the unit can earn the rent its price requires.
Why the 24.7% Vacancy Headline Misses the Top of the Market
Colliers reported a 24.7% vacancy rate for condos in Metro Manila in early 2026, representing around 75,000 empty units. The exit of POGO led to a loss of tenants, while the BSP’s rate hikes in 2024 made mortgage payments tougher. Many small investors who bought units during the boom were hoping to rent them out, but when they couldn’t find tenants or afford payments, they abandoned about 4,800 units in just the first quarter of 2025.
A ₱35-million unit in Makati has little competition. By early 2025, only 5% of high-end projects were unsold, according to Colliers. Lobien Realty Group reported an 85% take-up of upscale and luxury pre-selling properties by late 2025. Ayala Land’s 2026 data shows a similar trend: premium condominium sales increased by 29% in the first five months, while total residential sales dropped by 22% in the first half of the year.
| Measure | Metro Manila overall | Top tier (₱20M and up) |
|---|---|---|
| Unsold or vacant stock | 24.7% vacancy, about 75,000 units (early 2026) | High-end projects were about 5% of unsold inventory (early 2025) |
| Demand signal | About 4,800 buyer backouts in Q1 2025 | About 85% upscale and luxury pre-selling take-up (late 2025) |
| Ayala Land results | Residential sales take-up down 22% in H1 2026 | Premium condo sales up 29% in January–May 2026 |
| Who the buyer usually is | Small investors relying on rent and bank financing | End-user families and investors with large savings |
Sources: Colliers Philippines, Lobien Realty Group and Ayala Land disclosures, as cited at the end of this article.
The top tier isn’t immune; its risks come from a different angle, as shown by the Laurean pause.
Where vacancy is under 15%, where the glut really sits, and what Makati CBD rents look like below the luxury tier.
Laurean Residences: What Ayala Actually Paused

The project
Laurean Residences is the main residential building in Dela Rosa Gardens, Ayala Land’s redevelopment on Dela Rosa Street in Legazpi Village. Ayala Land Premier began selling it in late 2025, with prices starting at ₱35.7 million and exceeding ₱258 million.
Why Ayala hit pause
Ayala’s statement mentioned “growing cost pressures and uncertain delivery timelines.” The cause was the US–Iran conflict, which increased fuel, steel, and shipping costs. The Philippine Constructors Association projected that construction costs might go up by 10% to 30%. For a 67-storey tower, this kind of increase can determine if the project is profitable and raises concerns about the delivery date.
Ayala paused its operations as part of a larger change. It cancelled The Heights Katipunan in Quezon City, didn’t start any new residential projects in early 2026, and redirected funds to malls, hotels, and offices for steady income.
What buyers were offered
Buyers have three options. In April, Ayala mentioned a project review in mid-2027; in September, CEO Meean Dy confirmed the 2027 review, but no restart date was set.
Move your payments to another Ayala Land project with a clearer timeline, though probably not a comparable address.
Get back what you paid, plus interest. Your cash is free, but your place in the project is gone.
Keep your claim on a scarce address until Ayala decides in 2027, with your money tied up and no guaranteed restart.
Why Half the Buyers Chose to Wait
Dy stated in September, “50 percent chose to stay with us and wait for a decision.” That’s a significant figure for a project without a restart date. Three reasons account for this.
These buyers aren’t under pressure. A ₱35-million unit is usually purchased by buyers who can afford it easily. Many pay large down payments or in full, so they aren’t affected by rising rates. In Ayala’s residential projects, cancellations were high at 7.6% in the second quarter. Laurean’s buyers had a smooth exit, yet half still chose not to take it.
Waiting costs them little. Because Ayala offers refunds with interest, buyers who wait mainly lose access to their cash, as long as the refund option remains if the project doesn’t restart. This decision relies on trusting the developer to pay later, which is why the brand and financial stability are crucial at this price.
The address is hard to replace. Legazpi Village is located in Makati’s central business district, where available land is scarce and new luxury units often come from demolishing older buildings. A new four-bedroom unit there is rare and won’t be available again soon. Buyers who wanted that address had good reasons to hold onto it.
Mid-market investors walked away from about 4,800 units in early 2025 because their plans depended on tenants and bank loans. Laurean’s buyers were offered a paid exit, and half turned it down.
Both groups faced uncertainty. The difference was how much each one needed things to go to plan.
Sondris: Arthaland’s ₱12 Billion Read on Recovery

The project
Sondris is located on Arnaiz Avenue in Legazpi Village, where the former Atlas Land building site was. Arthaland, a smaller developer known for eco-friendly buildings, launched it in January 2026 with Japan’s Mitsui Fudosan. The project has 37 storeys and 252 units. The ₱12 billion mentioned is the expected revenue from unit sales, not the building costs.
The timing is important. Sondris was on sale when Ayala paused Laurean, so it didn’t respond to the pause. After that, Arthaland set a ₱12 billion revenue target on June 1 and started construction on June 17. It continued while its bigger neighbor halted.
Prices moved up, not down
The one-bedroom increased from ₱21 million in January to ₱22 million by June, about 5% rise in five months. By early July, 14% of the project was sold, with individual buyers purchasing smaller units and wealthy families from southern Metro Manila buying three-bedrooms.
| Unit | Size | Reported price | Approx. price per sqm |
|---|---|---|---|
| Sondris 1BR | 46 sqm | ₱22M (₱21M at launch) | about ₱478,000 |
| Sondris 2BR | Not disclosed | Not disclosed; about half of all units | — |
| Sondris 3BR | Not disclosed | About ₱72M | — |
| Sondris garden residence | 230 sqm | From ₱97M | about ₱422,000 |
| Laurean (paused) | 75–402 sqm | ₱35.7M to ₱258M+ | about ₱476,000–₱642,000 |
Price per sqm is U-Property PH’s arithmetic on reported starting prices. Actual prices vary by floor, view and payment terms.
How Arthaland is handling cost risk
Sondris faces the same cost risks as Laurean. Arthaland has chosen to secure costs early by fixing construction prices, negotiating supplier rates, and partnering with Lixil for long-term pricing on fixtures. A 37-storey building has less risk than a 67-storey one. The company aims for certifications like LEED, WELL, EDGE, and BERDE, with cooling systems designed to use at least 40% less electricity, benefiting buyers with lower power bills for years.
The Mitsui Fudosan factor
Mitsui Fudosan is a major property company in Japan, known as the “Tokyo Disneyland developer” because its former president helped create Oriental Land Co., which built Tokyo Disney Resort in 1960. For Sondris buyers, it’s important to know that Mitsui Fudosan invests in urban areas, providing strong support for a smaller Philippine developer.
In July 2026, the SEC fined Arthaland for misclassifying items in its cash flow statements. The company fixed the filings and paid the fine. While the fine doesn’t directly impact the project, it’s important for a buyer at this price to be aware of it.
Two Strategies, Side by Side
Put the two projects side by side, and the difference relies more on scale and exposure than on optimism.
| Laurean Residences | Sondris | |
|---|---|---|
| Developer | Ayala Land Premier | Arthaland, with Mitsui Fudosan |
| Location | Dela Rosa Gardens, Legazpi Village | Arnaiz Avenue, Legazpi Village |
| Height | 67 storeys (planned) | 37 storeys |
| Units and sizes | 1BR–4BR, 75–402 sqm | 252 units, 46–230 sqm |
| Entry price | ₱35.7M | ₱22M |
| Project scale | About ₱28B project value | About ₱12B projected revenue |
| Sales progress | More than ₱10B before the pause; all 4BR sold | About 14% sold by early July 2026 |
| Response to cost risk | Paused until costs and timelines are clearer | Locked in construction and supplier pricing, then broke ground |
| Status (Sept 2026) | Paused; review in 2027 | Under construction since June 17, 2026 |
Ayala is taking on a larger investment with a ₱28-billion, 67-storey tower, facing higher construction costs, while also having malls, offices, and hotels to invest in instead. Arthaland has a smaller tower with costs set before they could increase. Each company’s decision is logical for them, but neither indicates that the market has changed.
- 1Late 2025Ayala Land Premier launches Laurean Residences.
- 2January 2026Sondris launches, with one-bedroom units at ₱21 million.
- 3April 20, 2026Ayala pauses Laurean sales, citing costs and delivery risk from the US–Iran conflict.
- 4June 1, 2026Arthaland announces a ₱12 billion revenue target for Sondris.
- 5June 17, 2026Sondris breaks ground; the one-bedroom is now ₱22 million.
- 6September 8, 2026Ayala says half of Laurean’s buyers are staying; a decision will come in 2027.
Why Makati Still Holds the Top Tier
Arthaland referred to Makati as “the gold standard for luxury condo buyers,” and the data backs it up. Colliers observed that office, residential, and retail vacancies in Makati CBD are lower than the Metro Manila average. During the 2020–2021 downturn, prices in the upper-mid to ultra-luxury segments remained stable, while affordable segments dropped. Their research valued top-end Makati units at ₱700,000 to ₱900,000 per square meter.
Two main factors contribute to this situation. First, the land is limited. The central business district is nearly fully developed, with new luxury buildings replacing older ones, as seen with Sondris on the old Atlas Land site. Second, Ayala has a plan for the area focused on connectivity, mixed-use spaces, and greener, walkable streets, starting with Dela Rosa Gardens. The district continues to improve even as some towers are on hold.
BGC competes with newer buildings and wider streets, while Ayala’s Park East Place contributed to its 29% sales growth. Rockwell offers a quieter area. Makati’s strength lies in its established neighborhoods, corporate offices, embassies, and hotels, all close to the towers. For families wanting to live near work and school, this combination is hard to beat.
How a developer’s track record shows up in build quality, delivery dates and resale value, and how to check it before you commit.
What This Means for You
The best choice at this price depends on your reasons for buying. Here’s how the Laurean and Sondris stories relate to four common scenarios.
That ₱91,700 is the gross amount, excluding dues, taxes, empty months, and furnishings. Check the rental prices of similar units in the same village and see if a short-term or long-term lease is allowed by the building’s rules. For international buyers, the peso’s drop to ₱62.57 to the dollar reduces the dollar cost of a unit, but it increases the cost of imported materials, which developers will pass on through future price hikes.
If you’re holding a unit in a paused project
Laurean is the main case, but it might not be the only one. In April, Luna Securities chairman John Gatmaytan warned that other developers might stop their projects if the conflict continues. If that happens, you will likely have the same three options that Ayala suggested.
- You paid mostly in cash and won’t need the money soon.
- You want that specific address.
- The developer confirms in writing that the refund stays open.
- You planned a bank takeout or need the cash.
- Your plans depended on a move-in or rental date.
- The offer to refund later isn’t guaranteed in writing.
The law protects you even if a developer is not as generous as Ayala. Under PD 957, if a developer does not build as planned or on time, the buyer can stop payments and get back what they paid. Our guide to DHSUD’s new escrow rule for pre-selling payments explains how new projects need to safeguard buyers’ money before turnover.
What refunds, complaints and claims are available when a pre-selling project stalls, explained in practical terms.
The Risks Optimists Aren’t Pricing In
Arthaland’s gamble might pay off, but several factors could lead to failure, and these apply to any luxury pre-selling purchase in 2026.
- The conflict and construction costs. Locked-in contracts cover much of the risk, but a long conflict can still raise the price of anything not yet contracted and slow imported materials.
- More pauses. Analysts expect other developers to suspend projects if costs keep climbing. A pause ties up buyers’ money even when refunds are eventually paid.
- Pre-selling prices aren’t resale prices. Colliers found in early 2025 that Makati CBD pre-selling prices ran ₱267,000 to ₱400,000 per sqm above secondary-market prices. A pre-selling increase shows what the developer asks now, not what you could sell for later.
- Higher rates. The BSP raised its policy rate to 5.00% in August 2026, its third hike since April, which hits anyone planning a bank takeout at turnover.
None of these factors affect the top tier. They suggest judging a purchase based on its long-term value to you rather than its quick price increase. Our breakdown of the BSP’s Q3 2026 rate moves explains the impact of the August rate hike at turnover.
Signals to Watch Through 2027
The next year will reveal which developer understood the market best. Here are the signs to look for.
- Laurean’s 2027 review. A restart, redesign or cancellation will say more about Ayala’s view of costs than any statement.
- Sondris sales pace. Watch whether sales move well past 14% as the building rises.
- Ayala’s 2027 launches. After no new residential launches in the first half of 2026, where and at what price Ayala launches next will show how it reads premium demand.
- BSP rate decisions. More hikes squeeze buyers who plan a bank takeout at turnover.
- Quiet delays. A project that stops reporting progress without formally pausing can be riskier than an announced pause with clear buyer options.
Frequently Asked Questions
| Manila’s Condo Glut Isn’t Everywhere: Which Submarkets Actually Hold Value in 2026 The submarket-level view of the 24.7% vacancy figure. | → |
| Developer Bankrupt Mid-Construction: A Buyer’s Legal Playbook Your options if a pre-selling project stalls. | → |
| Temporary License to Sell: What DHSUD’s New Escrow Rule Means for Your Pre-Selling Payments How the new escrow rule protects money paid before turnover. | → |
| BSP Interest Rate Moves in Q3 2026: What It Means for Mortgage Rates and Buyer Affordability Why the August hike matters if you plan a bank takeout. | → |
| The Peso Just Hit a Record Low. Here’s What That Actually Means for Buying Property Right Now. What a weak peso changes for OFW and foreign buyers. | → |
Weighing a Makati Luxury Unit, or Holding One in a Paused Project?
Tell us your budget, how you plan to pay, and whether you’re buying to live in or to lease out. U-Property PH will walk you through the rent math, the contract terms to check, and which Makati addresses fit what you want.
This article is for general informational purposes only and does not constitute legal, financial, or professional advice. Market conditions, laws, regulations, and project terms change. Project details and prices are as reported by developers and the press through September 2026, and per-square-meter and yield figures are U-Property PH’s own illustrative arithmetic. Always consult a licensed real estate broker, lawyer, or tax professional for advice specific to your situation.
Sources
- Forbes, “Philippines’ Ayala Land Halts Sales Of Luxury Residential Tower As Costs Surge Amid Iran War” (April 2026) www.forbes.com
- BusinessWorld, “Ayala Land pauses Laurean unit sales, citing global conditions” (April 2026) bworldonline.com
- InsiderPH, “Why Ayala Land scrapped Katipunan and paused its Makati luxury project” (2026) insiderph.com
- InsiderPH, “The long game is alive at Ayala Land as its biggest believers stay the course” (September 2026) insiderph.com
- Rappler, “Luxury condo resilience: Half of Ayala’s Laurean buyers staying despite pause” (September 2026) www.rappler.com
- InsiderPH, “Makati, BGC projects drive Ayala Land luxury condo sales up 29%” (June 2026) insiderph.com
- Yahoo Finance, “Ayala Land Inc (Q2 2026) Earnings Call Highlights” (August 2026) finance.yahoo.com
- Philstar, “Ayala Land unveils new Makati township” (Dela Rosa Gardens, July 2025) www.philstar.com
- Context.ph, “Arthaland eyes P12B revenue from Makati luxury project” (June 2026) context.ph
- Inquirer, “Arthaland bets on Makati luxury market” (June 2026) business.inquirer.net
- BusinessMirror, “Arthaland sells 14% of Makati project” (July 2026) businessmirror.com.ph
- Manila Bulletin, “Tokyo Disneyland developer partners with Arthaland for luxury Makati tower” (June 2026) mb.com.ph
- Philstar, “Arthaland, Mitsui team up for Makati condo project” (November 2025) www.philstar.com
- Context.ph, “Arthaland fined by SEC for financial reporting errors” (July 2026) context.ph
- Oriental Land Co., “Beginning of the Oriental Land Co., Ltd.” (company history) www.olc.co.jp
- BusinessWorld, “Manila condo oversupply seen keeping vacancy high this year — Colliers” (February 2026) bworldonline.com
- Inquirer, “The upside in an uneven condo market” by Sheila Lobien (June 2026) business.inquirer.net
- InsiderPH, “Colliers PH: Metro Manila condo glut hits 8.2 years” (February 2025) insiderph.com
- BusinessWorld, “Premium real estate booms in Makati despite Metro Manila market trends” (Colliers, February 2025) www.bworldonline.com
Method: Project figures are as reported by the cited sources through September 2026. Price-per-square-meter figures divide reported starting prices by unit size. The rent needed for a 5% gross yield is the unit price multiplied by 5%, divided by 12 months.